The Government allows Ashtrom Group (Tase: ASHG) to plan and establish an electric station burned by the natural gas of Har TUV near beit shemesh. Ashtrom announced the TEV Aviv Stock Exchange (Spined a subsidiary to establish Shimshon Power Station, with Mega or Holdings processing at the National Powering Starts now. The power station is worth $ 1 billion
Today, there are no important power plants near Jerusalem. The closest stations are in Gezer and Tzafit, in Southern coastal plains. To resolve this, two new stations are planned: a station owned by the basic foundation to establish atarot industrialtrial zone in Jerusalem, and approved by the government in March, and Shimshon, now receiving approval. The two stations are currently in a preliminary planning periods, and after approval of the National Planning Committee they can apply for the government’s final approval to allow planning and construction to begin.
The power generation and energy storage
In announcing it in Tase, Ashtrom reported that the Shimshon station will make an electricity with a capacity of 830 MW, and also involve a storage facility. Storage facilities are usually used in solar energy fields to bridge peak gaps in the evening time to time development time in time development time during progress hours. In addition, such a facility can also buy energy from other sources, such as installing solar energy, and sell it in the same way.
The power station depends on the construction of overhead supply lines (400 kV), which should be established in 2030. Electric power can only commit production after that. The establishment station should also have a gas pipeline, after Israel’s gas lines in natural gas left plans to build one in the region, if it cannot connect to regional plants. A power plant as a “Anchor customer” to facilitate deployment of such an infrastructure tube, which is more accelerating for plants directly in gas supply.
Ashtrom said, “The power station will provide a solution to regional energy needs, including Jerusalem, which has now suffered a power infrastructure disability, and contributes to the National Grid.” Ashtrom added, it is a national significance project that can improve power supply levels in situations in the country to achieve the challenges of the event. “From the view of the ashtrom, it is an important step for it in the field of customary energy, with five conventional electric stations. Three approved by the ministry of financing before starting the financing (Kesem, Dalia 2 and Dalaa 2 and cared. In addition to the Har TUV plant there are four other power plutions in an advanced stage of the power supply, even in security and infrastructure for production possible to cut power prices.
Related articles
Ashtrom chairman rami nussbaum said, “The collaboration with tmega or and har tuv, who are among the strongest and leading players in the Israeli market, strengthens the financial and operational power station. The project constitutes a strategic milestone in the implementation of the ashtrom group’s growth and Expansion plans in the energy sector for the coming years. “
Published in Globes, Israel News in News – en.globes.co.il – On July 16, 2025.